Engineering report for the maintenance works of Abu Bakr Al-Seddiq modern School in Umbada Al-Jemaab neighborhood in Omdurman
(Revised Report)
Document number: NS-SV-OMD-19-01
Date: 21 October 2019
Revision 02
1 Introduction
The Sudan Renaissance Initiative aims to support and develop voluntary work in the rehabilitation of schools and public utilities.
Pilot Studies is conducted to organize the maintenance of schools. These studies provide a practical model for the various maintenance works in different areas. Three schools were selected to represent the three main areas of Khartoum State which include Omdurman, Khartoum and Khartoum Bahry.
A number of different neighborhood committees were contacted to nominate schools. The following schools were selected:
This engineering report presents the work of the field visit, the data collected and analyzed. The report also presents the technical recommendations that will be implemented by the Sudan Renaissance Initiative for Abu Bakr Al - Siddiq School in Umbada district, in Omdurman
2 Field visit
2-1 Date of visit
The main field visit was made to Abu Bakr Al-Siddeeq Model School on Saturday 12 October 2019.
The location of the school
The Abu Bakr Al-Siddiq Model School is located in the district of Umbada Al-Jumaab (according to the following coordinates: 32 ° 26'46.42 "E - 15 ° 39'42.61" N), serving a densely populated area, as shown in Figure 1.
3- The required maintenance works
Results of the field survey
3-1- Summary of the work currently required
The required maintenance work can be summarized urgently in:
3-2- Determining the priorities of maintenance works
Three key criteria were adopted when setting maintenance priorities:
Prioritization is also based on the ease with which the task can be completed, both physically and practically, where lower-cost work is prioritized to be more easily and fully accomplished.
Accordingly, the five problems identified were arranged in the following order:
Accordingly, it was recommended to start the work of maintenance of walls and the work of repainting and painting and installation of false ceilings and review the electrical recommendations and welding of broken desks, where item No. 7 will need a large budget difficult to provide at the moment, with the possibility of urgent maintenance of the walls of the toilets
3-3- The estimated cost of maintenance works
Initial estimates of the financial cost of the required business can be made as follows:
number | Item | Unit | Unit cost (pound) | Total cost (pound) |
1 | Maintenance of electrical connections, fans and bulbs | Provide technician for two days (Possibility to maintain the desks by welding in the same item) | 8000 | 8000 |
2 | Maintenance of external walls and toilets | Square meters | undefined | - |
3 | Creams for whites (different areas). | Square meters | undefined | - |
4 | Paints | Square meters | undefined | - |
5 | Making false ceilings for classes. | (4X 6 meters) 6 classes | 8,400 | 50,400 |
The prices of the remaining items will be estimated later.
3-4- Action Plan
The first mission started on Monday 21 October 2019.
This task is expected to be completed within four days, with tasks 2, 3, 4 and 5 starting from Saturday 26 October 2019. take advantage of evening, weekend or school holidays.
4- General recommendations for the development of educational performance in the school
4-1- Cooperation with Parents Council
The Fathers' Council is the primary and continuous source of material and moral support to improve educational performance and continuity.
4-2- Implementing the school health and safety system
The Sudan Renaissance Initiative will provide a basic first aid fund for the school, where a teacher is assigned to oversee the school's public health and safety.
A teacher will be trained in the concepts of Health & Safety for a comprehensive school application, reducing injuries and avoiding pupils from exposure to risk.
4-3- Activities during the summer vacation periods
The program will be used to utilize the capacity of students and teachers in maintaining and planting the school during school holidays.
The initiative will provide an integrated program of activities during the school holiday in cooperation with the school administration
SDG Goals
4- Quality Education
Project Type
Development, Humanitarian
Status
Vetted
Entity Type
NGO
Stage
Completed
Timeline
2020
Measurable Outcomes (Goals)
1- Maintenance of electrical connections, fans and bulbs.
2- Maintenance of desks and chairs.
3. Urgent maintenance work for the external walls and the walls of the toilets
4 - the work of whitewashed (scattered areas).
5 - the work of paints.
6 - Maintenance of false ceilings for the classes (the number of 6 classes).
7 - work toilets Siphon 10 toilets instead of toilets current pit.
The first mission started on Monday 21 October 2019.
This task is expected to be completed within four days, with tasks 2, 3, 4 and 5 starting from Saturday 26 October 2019.
, So you can take advantage of evening, weekend or school holidays.